Supreme Court Affirms Society’s Right to Replace- Defaulting Developer in Insolvency Context

Introduction
The Supreme Court’s ruling in A A Estates Pvt. Ltd. v. Kher Nagar Sukhsadan CHS Ltd. is a crucial
judgment on how redevelopment disputes interact with insolvency law. The case involved a Society
living in a dangerous, dilapidated building and a developer who failed to deliver the project for almost
two decades. When the Society terminated the developer and appointed a new one, the old developer
now under CIRP tried to use the IBC moratorium to block the redevelopment. The Court firmly held
that IBC cannot shield a non-performing developer, especially when agreements were already
terminated before insolvency and no property rights existed. The decision protects the rights of
residents awaiting safe housing and clarifies that public welfare and timely redevelopment outweigh
commercial claims under the IBC.
Table of Contents
Factual Background
The dispute arose from redevelopment of a 1956-constructed building belonging to the Kher Nagar
Sukhsadan Co-operative Housing Society. In 2005 and 2014, the Society executed a Development
Agreement and a Supplementary Agreement with A A Estates Pvt. Ltd. The developer was required to
provide rent compensation, secure approvals, demolish the old building, and complete reconstruction
within stipulated timelines. Despite nearly two decades, the developer failed to deliver. Out of 60
members, 41 never received any rent, and construction never commenced. Due to repeated delays and
non-performance, the Society issued termination notices in 2019 and 2021 all before the second CIRP.
Subsequently, in December 2023, the Society appointed Tri Star LLP as the new developer. The
Resolution Professional of A A Estates objected, invoking moratorium under Section 14, which led
the Society to approach the Bombay High Court. The High Court directed authorities to process
redevelopment permissions in favour of the new developer, prompting the present appeal.
Issues Before the Supreme Court
The Court considered four key questions:
- Whether termination of the 2005 and 2014 Development Agreements was valid.
- Whether development rights under these agreements constituted “assets” protected by Section
14 of the IBC. - Whether the High Court proceedings were vitiated for breach of natural justice.
- Whether the writ petition was maintainable despite an arbitration clause.
Court’s Analysis
1. Validity of Termination
The Court held that the Society had lawfully terminated the developer’s rights due to chronic delay
and failure to fulfil essential obligations. The termination occurred well before the second CIRP in
2022 and was based purely on contractual defaults, not insolvency. Referring to Gujarat Urja v. Amit
Gupta and TCS v. SK Wheels, the Court emphasized that NCLT cannot interfere with contractual
terminations unrelated to insolvency. Housing societies cannot be compelled to indefinitely tolerate
non-performance when the developer repeatedly defaults.
2. Development Rights Not Corporate Debtor’s Assets
The Court clarified that only existing, crystallised rights of the corporate debtor are protected by
moratorium. Development rights in this case were merely a contractual licence, not a proprietary or
possessory interest. The developer never had possession of the land; the Society and its members
remained in occupation. Therefore, no “asset” existed on the insolvency commencement date.
Moratorium under Section 14 cannot be invoked to revive long-terminated development agreements.
3. No Violation of Natural Justice
The appellants argued they were denied an opportunity to file a reply before the High Court. The
Supreme Court rejected this argument, noting that the developer’s counsel was present, did not seek
time, and participated in the hearing. Hence, no prejudice occurred.
4. Maintainability of the Writ Petition
The Court found the writ maintainable because the Society sought directions only against statutory
authorities (MHADA/MCGM). The reliefs did not require adjudication of inter-se contractual
disputes. Moreover, the building had been declared C-1 (dangerous), demanding urgent action to
protect residents’ safety under Article 21.
Judgment
The Supreme Court delivered a clear and categorical judgment dismissing the appeal filed by A A
Estates Pvt. Ltd. The Court held that the Housing Society had validly and lawfully terminated the
developer long before the second CIRP began. Therefore, no subsisting development rights remained
in favour of the corporate debtor on the insolvency commencement date. Crucially, the Court ruled
that the alleged “development rights” did not qualify as assets or property protected under the IBC
because the developer never had possession, never created any proprietary interest, and held only a
contractual licence that lapsed with termination. The moratorium under Section 14, meant to
safeguard existing assets, cannot revive expired contracts or prevent a society from protecting its
members’ safety.
The Court further emphasized that IBC is not a sanctuary for non-performing developers, especially
where the building is dangerously unfit for habitation and residents’ fundamental rights are at stake.
Upholding the Bombay High Court’s directions, the Supreme Court allowed redevelopment by the
new developer to proceed, holding that the welfare of 60 families cannot be compromised due to a
developer’s prolonged default.
Key Takeaways
This judgment sends a strong message that public interest and timely redevelopment take precedence
over commercial claims raised through insolvency proceedings. It clarifies that terminated
development agreements do not become “assets” merely because the developer enters CIRP, and
moratorium cannot be misused to obstruct redevelopment. The ruling strengthens the rights of
Housing Societies to act against chronic non-performance and reinforces that IBC cannot override
basic housing needs, safety concerns, or legitimate contractual termination. The decision will serve as
an important precedent in disputes where insolvent developers attempt to stall redevelopment projects
by invoking the moratorium.
Conclusion
This judgment reinforces that the IBC is not a tool for developers to stall redevelopment after years of
non-performance. It protects the rights of vulnerable residents in unsafe buildings and upholds a
society’s power to replace a defaulting developer even in the backdrop of insolvency proceedings. By distinguishing between contractual licences and proprietary assets, the Supreme Court has clarified
the true scope of Section 14 moratorium and prevented its misuse.
For further details write to contact@indialaw.in
By entering the email address you agree to our Privacy Policy.



